P-32, r. 1 - Regulation respecting Contracts of the Public Protector

Full text
75. If the Public Protector and the contractor cannot agree on the value of a change at the first negotiation, the detailed estimate of the change required is then determined by the Public Protector and paid according to the conditions stipulated in the contract.
Decision 1462-2, s. 75.